Post by: Boof63 on December 10, 2017, 05:18:29 AM
i have a tree  8 strings x 50 pix x 2 strands, in Xlights outputto lights songs play ok and effects are spot on
Use xschedule and effects are scrambled, other tree no problems.
Controller is Advatek Pixlite 16 Long range for this tree only.
All songs have been rendered to death, xl setup changed to 16 x 25 x 1+ zig zag at 25 - closer but still scrambled.
Any ideas please , tried chatt on ACL and that helped , but only found out about the difference between XL direct and XL sched. after shutting down show and playing to try and sort this out.
 HELP!!!!!
Cheers and thanks inadvance
Boof63 :-[ :'(
Title: Re: xl v xschedule
Post by: keithsw1111 on December 10, 2017, 10:11:29 AM
Have you run check schedule. Are you on the latest version .40
Title: Re: xl v xschedule
Post by: Boof63 on December 10, 2017, 01:58:16 PM
running version .40, check sequence showed render in canvas not erase mode, changed and rendered again. same result xl plays great. xschedule scrambles..
tried a new text file and same result, xl played directly from output lights = ok, use xsched and scrambled.
have deleted fseq to see if that fixes - same scrambling.
i am stumped
Cheers Boof63 :-\ :-\
Title: Re: xl v xschedule
Post by: keithsw1111 on December 10, 2017, 02:25:04 PM
But why didn't you run check schedule.
Title: Re: xl v xschedule
Post by: Boof63 on December 10, 2017, 05:36:58 PM
I ran check sequence as asked and it showed I was in canvas mode for rendering not erase mode. Reset to erase mode and re rendered . Text file was done in new rendering setup and still same result.
I have not run check sequence on text file seq. as had to go to work and didn’t think it would show anything. So will run when I get home. But otherwise any ideas if no error shows?
Cheers Boof63
Title: Re: xl v xschedule
Post by: keithsw1111 on December 10, 2017, 06:04:58 PM
Schedule ... not sequence.
Title: Re: xl v xschedule
Post by: Boof63 on December 10, 2017, 06:19:53 PM
Apologies - will run check schedule when I get home,
Thanks for your patience
Boof63 :-
Title: Re: xl v xschedule
Post by: Boof63 on December 11, 2017, 01:31:02 AM
hi again , no major hiccups with Xschedule - Check Schedule.
only listing for repeats of start and finishes for each show
Log file is below
So nothing i can see that explains the scrambling of the effects for this tree.
Cheers Boof63

First 6 strings play correctly, next 12 are scrambled

Checking schedule.

Full host name: ian-PC.lan
IP Address we are outputing data from: 10.1.1.203
If your PC has multiple network connections (such as wired and wireless) this should be the IP Address of the adapter your controllers are connected to. If it isnt your controllers may not receive output data.
If you are experiencing this problem you may need to set the local IP address to use.

Missing networks file
    No problems found

xSchedule show directory matches xLights
    ERR: xLights show directory D:\xLight2017 does not match xSchedule show directory D:\xLight2017\xmas 2017.

Inactive Outputs
    No problems found

Multiple outputs sending to same destination
    No problems found

Duplicate playlist names
    No problems found

Duplicate step names within a playlist
    ERR: Multiple playlists steps named 'Intro 2017' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.
    ERR: Multiple playlists steps named 'Intro 2017' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.
    ERR: Multiple playlists steps named 'finish 2017' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.
    ERR: Multiple playlists steps named 'finish 2017' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.
    ERR: Multiple playlists steps named 'Text Space' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.
    ERR: Multiple playlists steps named 'Intro 2017' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.
    ERR: Multiple playlists steps named 'finish 2017' exist in playlist 'show 2017 - All'. Commands which rely on step name may pick up the wrong one.

Duplicate schedule names within a playlist
    No problems found

Empty playlists
    No problems found

Empty steps
    No problems found

Steps with multiple FSEQs
    No problems found

FSEQs without 42445 channels
    No problems found

Steps with multiple audio
    No problems found

Steps with many videos
    No problems found

Duplicate matrix names
    No problems found

Matrices greater than available channels
    No problems found

Virtual matrices greater than available channels
    No problems found

Duplicate virtual matrix names
    No problems found

Output processing present
    No problems found

Multiple schedules with the same priority
    WARN: More than one schedule has priority 1. If these trigger at the same time then it is not certain which we will choose.
    WARN: More than one schedule has priority 6. If these trigger at the same time then it is not certain which we will choose.

No password set on website
    WARN: Website does not have a password set.

Non standard web port
    No problems found

Web in API only mode
    No problems found

Web server folder blank
    No problems found

Missing index.html
    No problems found

Missing referenced files
    No problems found

Check schedule done.
Errors: 8. Warnings: 3
Title: Re: xl v xschedule
Post by: keithsw1111 on December 11, 2017, 10:17:30 AM
The error message is right there - your show directories don’t match. That error is fatal. As long as that is true XLights and xschedule are extremely likely to produce different results.
Title: Re: xl v xschedule
Post by: Boof63 on December 12, 2017, 01:50:21 AM
Hi keith, thanks for your help changed schedule to main show folder not the subfolder where fseq were hiding and it works. Honestly not sure why? i was thinking it wrong as usual and so a BBBIIIGGGGG thanks. and hope us fools don't drive you to drink.
Is there any point in setting up sticky for us peeps to follow when we have problem?
ie Check sequence, check xschedule , check for overlaps etc,
a basic repair kit before we bother you ,gil, dan and the other gurus!!!
Cheers
Boof63 ;D ;D ;D
Title: Re: xl v xschedule
Post by: keithsw1111 on December 12, 2017, 10:17:52 AM
Mainly because no one reads sticky’s.